If you’ve recently built a house, shop, or office in Islamabad or Rawalpindi, you’ll need an electricity supply from IESCO (Islamabad Electric Supply Company). Many people think applying for a new connection is difficult, but the process is actually simple if you follow the right steps.
In this guide, we’ll explain how to apply for IESCO new connection, the required documents, fees, and how to track your application status.
Understanding IESCO New Connection
IESCO provides electricity to Islamabad, Rawalpindi, Attock, Jhelum, and Chakwal districts. If you live in these areas and need a new electricity meter, you must apply either online or by visiting your nearest IESCO office.
Methods to Apply for IESCO New Connection
There are two main ways to apply:
1. IESCO New Connection Online Apply
The government has introduced a simple online system called ENC (Electricity New Connection) to make the process easier.
Steps to apply online:
- Visit enc.com.pk
- Click on “Apply for New Connection”
- Select IESCO from the list of distribution companies
- Fill in the online form with:
- Applicant’s name
- CNIC number
- Mobile number
- Full address
- Load requirement (in kW)
- Upload scanned copies of documents (CNIC, property proof, etc.)
- Submit the form and save your Tracking ID
2. Apply Through IESCO Office
If you prefer offline submission, you can visit your local IESCO subdivision office.
Steps to apply at the office:
- Get the NEPRA New Connection Form from the office counter
- Fill in the details carefully
- Attach copies of the required documents
- Submit the application form and receive a tracking number
Documents Required for IESCO New Connection
Make sure you prepare these documents in advance to avoid delays:
- Copy of applicant’s CNIC
- Proof of ownership (registry, allotment letter, transfer letter, or sale deed)
- Site plan/map of the property
- Undertaking on stamp paper (as per IESCO format)
- Neighbor’s electricity bill (for address verification)
IESCO New Connection Fee
The IESCO new connection fee depends on the type of meter and load requirement:
- Single Phase Connection (up to 5 kW): Around Rs. 7,000 – Rs. 10,000
- Three Phase Connection (above 5 kW): Charges vary based on load demand
After your application is processed, you’ll receive a demand notice that clearly mentions the total fee. You must pay this fee at a designated bank branch to move forward with the installation.
IESCO New Connection Tracking
After applying, you can easily track your application status online.
Steps for tracking:
- Go to enc.com.pk
- Select “Track Application”
- Enter your Tracking ID or CNIC number
- The system will show your current application status
Installation and Meter Issuance
Once you’ve paid the demand notice fee:
- IESCO staff will visit your location for site inspection
- If everything is correct, your meter will be issued and installed
- Normally, the process takes 30 to 45 days, depending on the area and workload
Tips for a Smooth Application Process
- Keep all documents ready before applying
- Double-check details when filling out the form
- Pay the demand notice on time to avoid delays
- Use online tracking to stay updated instead of repeated office visits
Final Words
Applying for an IESCO new connection in Pakistan has become much easier, thanks to the online ENC system. Whether you choose to apply online or visit the IESCO office, the process is straightforward if you follow the steps and keep your documents ready.
With proper preparation, you can get your new electricity connection within a few weeks and enjoy uninterrupted power at your home or business.