How to Apply for LESCO new connection?

Lahore Electric Supply Company (LESCO) is one of Pakistan’s largest electricity distribution companies under WAPDA. It supplies power to Lahore, Kasur, Sheikhupura, Okara, and Nankana Sahib.

For residents and businesses in these areas, applying for a LESCO new connection is essential to access electricity legally.

How to Apply for LESCO New Connection?

The procedure for getting a new electricity connection from LESCO is transparent and straightforward. Applications are submitted online through the ENC portal, followed by document verification, fee payment, and meter installation.

Visit the ENC Portal

  • Open the official Electricity New Connection (ENC) website: www.enc.com.pk.
  • Select LESCO from the list of electricity companies.

Fill Out the Online Application Form

Provide the following information:

  • Applicant’s full name (as per CNIC)
  • Father’s/Husband’s name
  • CNIC number
  • Mobile number and email address
  • Complete property address
  • Type of connection (Domestic, Commercial, Industrial, or Agricultural)
  • Required load in kW

Upload Required Documents

Scan and upload all necessary documents:

  • Copy of applicant’s CNIC
  • Proof of property ownership (Registry, Allotment letter, Sale deed, or Fard)
  • Attested affidavit by the applicant
  • Neighbor’s electricity bill copy or reference number
  • Undertaking form (available on ENC portal)
  • Permission letter from landlord (for rented property)

Submit the Application

  • Double-check all information before submitting.
  • Once submitted, you will receive a tracking ID to check the progress online.

Print and Submit to LESCO Office

  • Print the submitted application form.
  • Attach attested copies of all documents.
  • Submit them at your nearest LESCO Customer Service Center for processing.

Demand Notice (DN) Payment

After verification, LESCO will issue a Demand Notice.

  • Pay the fee at the designated bank.
  • Keep the receipt safe for further verification.

Meter Installation

  • After fee verification, LESCO officials will conduct a site inspection.
  • Once cleared, your electricity meter will be installed, and the new connection will be activated.

Documents Required for LESCO New Connection

Here’s the complete checklist:

  • CNIC copy of applicant
  • Property ownership proof (Registry, Sale deed, Fard, or Allotment letter)
  • Attested affidavit by applicant
  • Neighbor’s bill or reference number
  • Undertaking form (download from ENC portal)
  • Permission letter from landlord (if rented property)

LESCO New Connection Fee

The LESCO connection fee depends on:

  • Type of connection (Domestic, Commercial, Industrial, or Agricultural)
  • Load requirement (in kW)
  • Distance from main supply line

How to Track LESCO New Connection Application?

To track your application status:

  1. Visit the ENC tracking page.
  2. Enter your tracking ID.
  3. View the status (Pending, Verified, Demand Notice Issued, or Installed).

Final Thoughts

Applying for a LESCO new connection in Pakistan is now more convenient with the ENC system. By completing the online application, submitting documents, and paying the Demand Notice on time, you can get your new electricity meter installed without unnecessary delays.

If you live in Lahore, Kasur, Sheikhupura, Okara, or Nankana Sahib, always use the official ENC portal and LESCO offices to avoid scams.